Dynamics AX Sustained Engineering: KB 2887723 - Consume on-hand inventory after consuming supply orders
Источник: http://blogs.technet.com/b/dynamicsa...ly-orders.aspx
==============

This blog describes the change in behavior for the consumption of on-hand inventory in relation to other supply, during planning and explosion related to KB 2887723 - Consume on-hand inventory after consuming supply orders.


Microsoft Dynamics AX2012R2



Consume on-hand inventory BEFORE all other supply



Delivery date control Capable to Promise (CTP) during sales order entry will use on-hand inventory for the first order, regardless of the delivery date. This can lead to situations where CTP is unable to fulfill the desired order date, even when on-hand inventory is available.

Consuming on-hand inventory before incoming supply ensures that the planner will always receive action messages to reduce or cancel superfluous supply orders for the period.



Scenario 1:

In this scenario, we have 1 pc. of on-hand inventory and two firmed supply orders for 1 pc. each (Supply A and Supply B).

A sales order for 2 pcs. is entered on a date after the last supply (Demand A).

On-hand inventory and Supply A will be used to fulfill the demand.

Supply B is not used for any demand, so an action message to cancel the order is created.



Now we enter another sales order with a delivery date prior to the first supply (Demand B).

As the on-hand inventory is used to fulfill the first sales order, we cannot fulfill the second order.



Microsoft Dynamics AX2012R2 with KB 2887723

Consume on-hand inventory AFTER all other supply

Delivery date control Capable to Promise (CTP) during sales order entry will not use on-hand inventory until all supply orders that are due during the positive days interval are used. This ensures that CTP saves the on-hand inventory for possible subsequent sales orders.

However, in the situation where there are no additional sales orders, the on-hand inventory will remain as is - without any action message to reduce supply orders.

Scenario 2:

As in Scenario 1 we have 1 pc. of on-hand inventory, and two firmed supply orders for 1 pc. each (Supply A and Supply B).

A sales order for 2 pcs. is entered on a date after the last supply (Demand A).

With the changes from KB 2887723, Supply A and Supply B will be used to fulfill the demand, and the on-hand inventory will be left for possible subsequent orders.

However, now Supply B is used to fulfill the first sales order and hence you will not get an action message to cancel it.



Now we enter the second sales order with a delivery date prior to the first supply (Demand B).

As the on-hand inventory is free, we can use this to fulfill the second order.






Источник: http://blogs.technet.com/b/dynamicsa...ly-orders.aspx
__________________
Расскажите о новых и интересных блогах по Microsoft Dynamics, напишите личное сообщение администратору.
 

Похожие темы
Тема Автор Раздел Ответов Посл. сообщение
Dynamics AX Sustained Engineering: Announcing Cumulative Update 6 for Microsoft Dynamics AX 2012 R2 Blog bot DAX Blogs 0 15.12.2013 02:18
Dynamics AX Sustained Engineering: Announcing Cumulative Update 4 for Microsoft Dynamics AX 2012 & Microsoft Dynamics AX 2012 Feature Pack 1 Blog bot DAX Blogs 0 05.12.2012 01:11
Dynamics AX Sustained Engineering: Announcing Rollup 8 for Microsoft Dynamics AX 2009 SP1 Blog bot DAX Blogs 0 22.03.2012 22:11
Dynamics AX: Managing Your Supply Chain Using Microsoft Dynamics AX 2009 - Book Review Blog bot DAX Blogs 0 31.03.2009 23:06
Dynamics AX Sustained Engineering: Microsoft Dynamics AX 2009 Service Pack 1 Released Blog bot DAX Blogs 5 21.11.2008 17:00

Ваши права в разделе
Вы не можете создавать новые темы
Вы не можете отвечать в темах
Вы не можете прикреплять вложения
Вы не можете редактировать свои сообщения

BB коды Вкл.
Смайлы Вкл.
[IMG] код Вкл.
HTML код Выкл.
Быстрый переход

Рейтинг@Mail.ru
Часовой пояс GMT +3, время: 20:47.